ATTENTION! Blockade Hochkar Alpenstraße - road rehabilitation

Work on the rehabilitation of the Hochkar Alpine road above Aibl will begin on 18 May 2020. The construction work will result in the following traffic restrictions:

Construction phase 1 - Rock removal / widening in the area of Lichtreith to Gamsmauer
From 18 May to 05 June 2020 - Closure in the period from 07:30 to 18:00

On weekends and public holidays (Fridays) the carriageway is open to traffic at least halfway.

Stage 2 - Construction of substructure and asphalt
From 18 June to 26 June 2020 - half-sided barrier with traffic stops (stops up to 30 min.)
In the period from 22 June to 26 June 2020, there may also be a one-day closure (07:30 to 18:00).

TOTAL BARRY FROM 29 June to 03 July 2020

On weekends and public holidays (Fridays) the carriageway is open to traffic at least halfway.

The restrictions apply to all road users - including pedestrians and cyclists ! In case of construction-related changes, delays due to bad weather etc. the municipality will keep you informed ! A very tight schedule for the construction work has been set by the planning and the building supervision authority so that the Hochkar road can be used without any obstructions when the holidays start again. Thank you very much for your understanding!